Ordering too little concrete stops a pour in its tracks. Ordering too much wastes money and leaves you with leftover mix that has to be dumped. The Concrete Calculator turns a few dimensions into volume (cubic feet, cubic yards, and cubic meters), a bag count for 40/60/80 lb premix, and an optional cost estimate — all in the browser, with no signup.
This guide walks through the four shapes the tool covers, the bag-yield math suppliers actually use, and the waste factor that keeps a job from running short. Whether you are pouring a patio, a footing, a sonotube pier, or a row of fence posts, you can size the order before you buy.
Every calculation stays on your device. You can work from a job site with a weak signal and copy the result into a materials list without uploading project data.
Why Use the Concrete Calculator?
- Four pour shapes, one form. Slab, footing, column, and post hole cover the pours most homeowners and small contractors actually do.
- Imperial and metric without retyping. Switch between feet/inches and meters/centimeters; volume is shown in ft³, yd³, and m³ at the same time so any supplier quote makes sense.
- Bag yields that match the bag. 40 lb bags yield 0.30 ft³, 60 lb bags 0.45 ft³, and 80 lb bags 0.60 ft³ — the figures printed on typical premix sacks.
- Waste is built in. A default 10% waste factor and a round-up to whole bags means you do not finish a slab one bag short.
- Cost before you leave the lot. Enter a price per bag and the tool multiplies it by the rounded bag count.
- Private by design. No accounts, no uploads, no telemetry. Dimensions never leave the browser.
Key Features
| Feature | What it does |
|---|---|
| Shape modes | Slab and footing use length × width × depth; column and post hole use π × r² × h |
| Unit systems | Imperial (ft / in) or metric (m / cm) |
| Volume output | Cubic feet, cubic yards, and cubic meters together |
| Bag sizes | 40 lb (0.30 ft³), 60 lb (0.45 ft³), 80 lb (0.60 ft³) |
| Waste factor | Percentage extra, default 10%, applied before rounding bags up |
| Cost estimate | Optional price per bag × bags needed |
| Formula line | Shows the exact volume expression used for the current shape |
| Copy / clear | Copy a materials summary or reset the form |
Depth and height are entered in inches (imperial) or centimetres (metric), while length, width, and diameter use feet or metres. That matches how plans are written: a 4-inch slab on a 10-by-12-foot pad, or a 10-centimetre slab on a 3-by-4-metre pad.
Bag count is always computed from cubic feet, because premix yields are published in ft³. Metric inputs are converted internally so an 80 lb bag still means 0.60 ft³ of mix, not a different product.
How to Use
- Open the Concrete Calculator and pick a shape: Slab (patio, driveway, floor), Footing (trench under a wall), Column (sonotube, pier), or Post Hole (fence or deck post).
- Choose Imperial (ft / in) or Metric (m / cm). Enter length and width for rectangles, or diameter for round pours. Enter depth (slab/footing) or height (column/hole) in inches or centimetres.
- Select a bag size. Use 80 lb bags for large slabs if you can lift them; 40 lb or 60 lb bags for posts and tight access. Leave waste at 10% unless the pour is unusually clean or messy.
- Optionally type a cost per bag. The result panel shows bags needed, ft³ / yd³ / m³, estimated total, and the volume formula.
- Copy the summary into a shopping list, or clear the form and size the next pour. Ready-mix trucks are quoted in cubic yards — use that number when 1 yd³ or more is cheaper than bags.
Understanding Concrete Volume, Bags, and Waste
Concrete volume is geometry first. A slab or footing is a rectangular box:
Volume = length × width × depth
A column or post hole is a cylinder:
Volume = π × r² × h (radius is half the diameter)
The calculator converts depth and height into the same linear unit as length before multiplying. Imperial depth in inches is divided by 12; metric depth in centimetres is divided by 100. That is why a 4-inch slab on a 10 × 12 ft pad is 10 × 12 × (4/12) = 40 ft³.
Ready-mix is sold by the cubic yard. There are 27 cubic feet in a cubic yard, so 40 ft³ is 40 ÷ 27 ≈ 1.48 yd³. Cubic metres are shown as well (1 ft³ ≈ 0.0283 m³) for metric suppliers.
Premix bags are sold by weight, but coverage is published in cubic feet:
- 40 lb ≈ 0.30 ft³
- 60 lb ≈ 0.45 ft³
- 80 lb ≈ 0.60 ft³
Bags needed = ceil( (cubic feet ÷ yield per bag) × (1 + waste%) ). The default 10% waste covers uneven subgrade, over-excavation, spillage, and the last bit of a form that never fills as neatly as the drawing. The tool always rounds up, because you cannot buy 0.4 of a bag on a Saturday morning.
A rule of thumb: bags make sense under about 1 cubic yard (27 ft³). Above that, a short-load ready-mix truck is usually cheaper and far less mixing. The calculator still reports both yardage and bags so you can compare.
Practical Use Cases
Patio or shed slab
A 10 ft × 12 ft patio at 4 inches thick is 40 ft³, or 1.48 yd³. With 10% waste and 80 lb bags: (40 ÷ 0.60) × 1.10 ≈ 73.3, rounded up to 74 bags. At $7.50 per bag that is about $555 of mix before rebar, mesh, or a pump. If a local plant quotes $180 per yard with a 1-yard minimum, the truck wins on cost and labour. Use bags when you cannot get a chute to the backyard.
Driveways often need 4–6 inches. Doubling thickness from 4 to 6 inches on the same 10 × 12 pad jumps volume from 40 to 60 ft³ (2.22 yd³). Check the thickness on the drawing before you order.
Wall footing
A 20 ft footing, 18 inches wide and 8 inches deep: 20 × 1.5 × (8/12) = 20 ft³. With 60 lb bags and 10% waste: (20 ÷ 0.45) × 1.10 ≈ 48.9 → 49 bags. Footings are long and narrow; the Footing mode is the same math as a slab, but the description reminds you that you are filling a trench, not a pad. Keep waste at 10–15% if the trench walls are rough.
Sonotube deck piers
A 12-inch-diameter tube, 4 ft of pour height: r = 0.5 ft, volume = π × 0.5² × 4 ≈ 3.14 ft³. With 80 lb bags and 10% waste you need 6 bags per pier. Four corners of a small deck are 24 bags — still a bag job, not a truck. Switch to Column mode, enter diameter in feet (or metres) and height in inches (48 in).
Fence post holes
Eight 10-inch-diameter holes, 24 inches deep: each hole is π × (5/12)² × 2 ≈ 1.09 ft³. Eight holes ≈ 8.72 ft³. With 60 lb bags and 10% waste: about 22 bags for the set. Use Post Hole mode for one hole, then multiply bags by the number of posts if they are identical — or run the calculator once per size if posts differ.
Best Practices
- Measure the hole, not the lumber. A 4×4 post sits in a hole that is often 10–12 inches across. Diameter of the excavation is what the mix fills.
- Keep thickness honest. A patio specified at 4 inches that is scraped to 3 inches at the edges will still need mix for 4 inches if you strike off to the forms. Order for the form, not the optimistic average.
- Do not skip waste on the first pour of the day. Cold joints from running out mid-slab are expensive. 10% is the default for a reason.
- Match bag size to the crew. 80 lb bags are fewer trips but harder on backs and stairs. 40 lb bags cost more per cubic foot; use them when access is tight.
- Use cubic yards for anything over ~1 yd³. The Volume Calculator is useful if you need a raw geometric volume without bag math; come back here when you need premix counts.
- Convert odd plan units first. If a drawing mixes millimetres and feet, use the Unit Converter so every field in the concrete tool is in one system.
Size the pour before you mix
Open the Concrete Calculator, pick the shape that matches the form, and enter the dimensions from the tape, not from memory. You will get volume in three units, a rounded bag count with waste, and a cost figure you can take to the store. That is the whole point: finish the pour in one go, without a leftover pallet or a dead truck waiting on a second load.
Related Tools You Might Like:
- Volume Calculator — cubes, cylinders, and other solids when you need geometry without bag yields
- Unit Converter — length, area, and volume units before you enter dimensions
- Surface Area Calculator — form face area for sealer, paint, or form-release estimates
Happy pouring.